ISO-Plane TRL3 Workpackage
Technical Work Packages
The TRL3 phase is organized around technical work packages.
Each work package must produce a documented engineering output that can be reviewed, challenged and improved by the project team.
| Work Package | Main Objective | TRL3 Output |
|---|---|---|
| WP1 — Structural Engineering | Validate the feasibility of the primary structure | Structural models, load cases, stress results |
| WP2 — Aerodynamics and Performance | Refine aerodynamic assumptions | CFD results, drag breakdown, performance update |
| WP3 — Cargo Handling System | Validate lifting kinematics and load paths | Mechanism study, load transfer report, FMEA |
| WP4 — Ventral Door System | Size and validate the lower cargo opening concept | Door sizing, hinge loads, sealing concept |
| WP5 — Landing Gear Integration | Verify compatibility between landing gear and cargo bay geometry | Gear packaging and structural integration report |
| WP6 — Mass and Balance | Consolidate the mass model and CG envelope | Updated weight statement and balance charts |
| WP7 — Systems Architecture | Define preliminary aircraft systems interfaces | System block diagrams and interface matrix |
| WP8 — Risk and Safety | Identify and reduce major technical risks | Risk register, mitigation plan, preliminary FMEA |
| WP9 — Industrial Interface | Prepare technical exchanges with partners | Briefing package and supplier question list |
WP1 — Structural Engineering
Purpose
The structural engineering work package is central to TRL3.
Its purpose is to validate that the ISO-Plane can integrate a large cargo bay and ventral opening while maintaining sufficient structural integrity for flight, landing, pressurization and cargo handling loads.
Main Structural Questions
The key questions are:
- Can a fuselage of approximately 4 m diameter support a large ventral opening?
- Can the cargo bay remain pressurized with acceptable structural mass?
- Can the central wing box transfer loads without obstructing the cargo bay?
- Can container lifting loads be transferred safely into primary fuselage frames?
- Can the landing gear loads be routed through the nacelles and wing structure without excessive reinforcement?
- Can fatigue-sensitive zones be identified early?
Structural Analysis Scope
The structural analysis shall include:
- fuselage shell modelling;
- frame and stringer preliminary sizing;
- floor beam modelling;
- central wing box modelling;
- cargo bay reinforcement modelling;
- ventral door frame modelling;
- landing gear load introduction zones;
- engine nacelle support loads;
- lifting arm attachment zones;
- twist-lock load introduction zones;
- local stress concentration assessment.
Primary Load Cases
TRL3 structural load cases include:
| Load Case | Description | Critical Zones |
|---|---|---|
| Pressurization | Differential pressure between cargo bay and atmosphere | fuselage shell, door seals, pressure frames |
| Cruise flight | Wing bending, fuselage bending, engine loads | wing box, fuselage frames, nacelles |
| Landing | Vertical and longitudinal gear loads | nacelles, wing structure, gear attachments |
| Container lifting | Concentrated lifting loads from ISO corner interfaces | robotic arms, floor beams, frames |
| Asymmetric lift | Uneven load distribution during container handling | arm attachments, fuselage torsion paths |
| Ground handling | Loads during loading from ground or truck trailer | landing gear, cargo bay, door structure |
| Emergency securing | Container restraint under abnormal accelerations | twist-locks, cargo floor, fuselage hard points |
Fuselage Structural Challenge
The fuselage is one of the most critical elements of TRL3.
A conventional pressurized fuselage relies on circumferential continuity. The ISO-Plane breaks this continuity by introducing a large ventral opening.
This creates several structural challenges:
- loss of lower fuselage stiffness;
- local stress concentrations around door cut-outs;
- increased frame loads near opening edges;
- fatigue risk near reinforced corners;
- pressurization sealing complexity;
- interaction between cargo floor and fuselage shell;
- need for strong but lightweight door locking mechanisms.
Central Wing Box Challenge
The central wing box must transfer the aerodynamic loads from the high wing into the fuselage while preserving the usable cargo volume.
The TRL3 analysis shall verify:
- box height and width compatibility with cargo bay geometry;
- wing bending load transfer;
- torsional stiffness;
- interaction with pressurized fuselage structure;
- possible local reinforcement requirements;
- accessibility for inspection and maintenance.
Structural Deliverables
The expected deliverables of WP1 are:
- preliminary finite element model of the fuselage;
- preliminary finite element model of the wing box;
- local model of the ventral door frame;
- load case definition document;
- stress map of critical zones;
- first mass estimate of reinforcements;
- list of structural assumptions requiring TRL4 testing.
WP2 — Aerodynamics and Performance
Purpose
The aerodynamic work package aims to refine the flight performance assumptions made during TRL2.
At TRL3, the aircraft geometry must be assessed with more rigorous aerodynamic tools.
Aerodynamic Topics
The aerodynamic studies shall include:
- high-wing aerodynamic performance;
- fuselage drag assessment;
- nacelle drag and interference effects;
- propeller slipstream interaction;
- tailplane effectiveness;
- rear fuselage flow behaviour;
- drag impact of landing gear fairings and nacelles;
- effect of cargo door geometry on external shape;
- takeoff and landing performance;
- climb performance;
- cruise performance;
- payload-range update.
CFD Scope
CFD studies should be progressively introduced.
Initial CFD may use simplified models, followed by more refined geometry as the digital mock-up matures.
The CFD programme should cover:
- clean cruise configuration;
- takeoff configuration;
- landing configuration;
- nacelle-wing interaction;
- fuselage-wing interference;
- propeller slipstream approximation;
- empennage effectiveness;
- sensitivity to angle of attack;
- sensitivity to sideslip.
Drag Breakdown
A TRL3 drag breakdown should distinguish:
- fuselage parasite drag;
- wing profile drag;
- induced drag;
- nacelle drag;
- landing gear fairing drag;
- tail drag;
- cooling and inlet drag;
- interference drag;
- trim drag;
- residual modelling uncertainty.
Performance Outputs
The TRL3 performance model shall update:
- cruise speed estimate;
- takeoff distance;
- landing distance;
- climb gradient;
- fuel burn;
- mission range;
- payload-range curve;
- service ceiling estimate;
- reserve fuel assumptions.
Aerodynamic Risks
The main aerodynamic risks are:
- excessive drag due to large fuselage diameter;
- interference between nacelles and high wing;
- insufficient tail effectiveness;
- trim penalty caused by cargo bay and CG constraints;
- aerodynamic penalty of structural reinforcements;
- possible aeroelastic sensitivity of the high-wing configuration.
WP3 — Cargo Handling System Validation
Purpose
The cargo handling system is one of the most innovative and highest-risk subsystems of the ISO-Plane.
At TRL3, this system moves from conceptual feasibility toward engineering verification.
The objective is to demonstrate that the autonomous loading concept is mechanically credible, structurally compatible and operationally safe.
System Description
The cargo handling system is intended to lift, position, secure and release one 20-foot ISO container.
The system may include:
- mechanized or robotic lifting arms;
- twist-lock interfaces;
- guidance rails or alignment aids;
- emergency winches;
- local structural hard points;
- sensors for position detection;
- control logic from the cockpit;
- mechanical locking systems;
- emergency release procedures.
Validation Pillar 1 — Kinematic Realism
The first TRL3 validation pillar is kinematic realism.
The mechanism must physically fit inside the aircraft and execute its deployment sequence without collision.
The analysis shall cover:
- arm deployment sequence;
- articulation limits;
- retraction envelope;
- clearance with fuselage frames;
- clearance with the ventral door panels;
- clearance with the container;
- compatibility with truck trailer height;
- ground loading geometry;
- emergency retraction cases;
- maintenance access.
A major TRL3 objective is to detect early geometric conflicts that were not visible at TRL2.
Validation Pillar 2 — Structural Load Transfer
Lifting an 8-tonne container generates concentrated loads at the ISO corner interfaces.
The load path must be understood from the container to the aircraft primary structure.
The load path includes:
- ISO corner casting;
- twist-lock interface;
- lifting arm end effector;
- arm structure;
- actuator or linkage system;
- arm root attachment;
- fuselage frame or floor beam;
- primary fuselage reinforcement;
- global aircraft structure.
Load Cases for Cargo Handling
The cargo handling simulations shall include:
- symmetric vertical lift;
- asymmetric lift;
- container offset in longitudinal direction;
- container offset in lateral direction;
- angular misalignment;
- dynamic amplification during lifting;
- emergency stop;
- partial arm failure;
- failed twist-lock engagement;
- winch-assisted recovery;
- truck trailer loading case;
- ground loading case.
Validation Pillar 3 — Safety and Redundancy
Autonomous container handling requires fault tolerance.
TRL3 shall define a preliminary safety architecture covering:
- loss of one lifting arm;
- actuator jam;
- twist-lock failure;
- sensor failure;
- emergency lowering;
- emergency winch recovery;
- power loss during loading;
- communication failure between cockpit and handling system;
- mechanical over-travel protection;
- ground personnel exclusion zone.
Preliminary FMEA
A preliminary Failure Mode and Effects Analysis shall be performed.
| Failure Mode | Possible Effect | TRL3 Mitigation |
|---|---|---|
| One arm fails during lift | Asymmetric container load and possible structural overload | emergency winch support, load sensors, automatic stop |
| Twist-lock fails to engage | Container not secured | lock status detection, cockpit warning, mechanical inspection logic |
| Door does not fully open | Collision risk during lifting | position sensors, interlock logic |
| Power loss during lift | Container suspended or partially lifted | mechanical brakes, backup power, emergency lowering |
| Misalignment with truck | Excessive side load on arms | alignment sensors, tolerance envelope, no-lift condition |
| Sensor error | Incorrect positioning | redundant sensing, manual verification mode |
Ground Clearance Studies
TRL3 shall confirm that loading and unloading remain feasible on realistic airfield surfaces.
The studies shall account for:
- landing gear compression;
- tire deflection;
- ground slope;
- truck trailer height variability;
- uneven terrain;
- container support height;
- clearance between container and fuselage;
- door clearance during opening;
- propeller and ground safety zones.
Primary Objective of WP3
The cargo handling system shall demonstrate credible mechanical integration with controlled load paths, manageable risk and aviation-level safety logic.
WP4 — Ventral Cargo Door System
Purpose
The ventral cargo door is both a structural system and a functional enabler of the ISO-Plane mission.
Its TRL3 validation is therefore critical.
Door Functional Requirements
The ventral cargo door shall:
- provide access for a 20-foot ISO container;
- support loading from ground level;
- support loading from a truck trailer;
- preserve fuselage pressure integrity;
- maintain aerodynamic smoothness in flight;
- provide reliable locking;
- allow safe opening and closing on the ground;
- integrate with the cargo handling system;
- remain inspectable and maintainable;
- avoid unacceptable mass penalty.
Three-Panel Concept
The retained TRL3 concept is based on a three-panel opening mechanism.
This architecture separates functions between door panels and movable floor or access structures.
The three-panel approach is intended to reduce individual panel size and simplify certain mechanical functions, while introducing additional hinges, actuators and locking points.
Engineering Questions
The TRL3 door analysis shall answer:
- What are the hinge loads during opening and closing?
- What are the pressurization loads in flight?
- What reinforcement is required around the cut-out?
- What locking architecture is required?
- How are loads transferred into fuselage frames?
- How is sealing achieved?
- How is the door inspected?
- What happens if one actuator fails?
- Can the door be closed manually or through emergency backup?
- What is the mass penalty of the door and surrounding reinforcements?
Door Load Cases
| Load Case | Description | Critical Element |
|---|---|---|
| Pressurized cruise | Door loaded by cabin differential pressure | seals, locks, frame |
| Door opening | Gravity and actuator loads during ground opening | hinges, actuators |
| Door closing | Alignment and locking loads | latch system |
| Ground handling | Possible local loads from cargo operations | lower frame, local panels |
| Emergency failure | One actuator or lock unavailable | redundancy architecture |
Door Deliverables
The TRL3 door package shall include:
- door kinematic model;
- preliminary hinge sizing;
- preliminary actuator sizing;
- locking concept;
- sealing concept;
- structural reinforcement map;
- failure scenarios;
- mass estimate;
- TRL4 test recommendations.
WP5 — Landing Gear Integration
Purpose
The landing gear integration work package verifies that the Q400-derived landing gear concept is compatible with the ISO-Plane architecture.
The main landing gear must not interfere with the cargo bay or ventral door.
Integration Rationale
A fuselage-mounted landing gear would conflict with the ventral cargo opening.
A nacelle-mounted main landing gear offers a more compatible integration path because it preserves the lower fuselage volume for the cargo bay and door.
TRL3 Landing Gear Studies
The TRL3 work shall include:
- nacelle structural reinforcement;
- gear bay packaging;
- retraction mechanism study;
- wheel clearance;
- gear door integration;
- landing load path analysis;
- braking energy assessment;
- turning radius estimation;
- ground stability during loading;
- compatibility with motorized nose gear concept.
Ground Stability During Loading
The aircraft must remain stable while a container is lifted, lowered or transferred from a truck.
TRL3 shall verify:
- aircraft tipping margins;
- longitudinal stability;
- lateral stability;
- CG shift during lift;
- landing gear load redistribution;
- braking or parking requirements;
- ground slope sensitivity;
- wind sensitivity during loading.
Landing Gear Deliverables
The expected deliverables are:
- landing gear integration drawing;
- nacelle structural concept;
- gear retraction envelope;
- preliminary landing load calculation;
- ground stability analysis;
- brake energy estimate;
- list of Q400-derived elements requiring redesign or adaptation.
WP6 — Mass and Balance Consolidation
Purpose
Mass and balance consolidation is required to determine whether the ISO-Plane architecture remains feasible after adding the structural reinforcements and mechanisms identified during TRL3.
Mass Breakdown
The updated mass breakdown shall include:
- fuselage structure;
- wing and central wing box;
- empennage;
- engines and nacelles;
- landing gear;
- cargo door system;
- cargo handling system;
- cockpit systems;
- fuel system;
- electrical systems;
- hydraulic systems;
- avionics;
- environmental control system;
- interior and cargo bay equipment;
- operational items;
- payload;
- fuel.
CG Envelope
The center-of-gravity study shall include:
- empty aircraft CG;
- fuel loading effect;
- container installed position;
- container lifting transition;
- loading from ground;
- loading from truck;
- asymmetric loading scenarios;
- emergency unloading scenarios;
- takeoff CG envelope;
- landing CG envelope.
Critical CG Situation
The most critical CG condition may occur during partial container lift, when the container is not yet fully secured in the cargo bay and the aircraft receives temporary external loads through the handling mechanism.
TRL3 shall explicitly model this transient phase.
Mass Control Objective
The main mass objective is to confirm the feasibility of an approximately 30-tonne-class MTOW configuration.
At TRL3, this figure remains a target requiring consolidation.
The main mass risk is the accumulation of reinforcements for:
- ventral opening;
- pressurized cargo bay;
- lifting arms;
- landing gear integration;
- central wing box;
- locking mechanisms;
- safety redundancy systems.
WP7 — Systems Architecture Refinement
Purpose
TRL3 shall define the preliminary architecture of major aircraft systems and their interfaces with the cargo mission equipment.
Systems to be Addressed
The systems architecture shall include:
- electrical power distribution;
- hydraulic power distribution;
- cargo handling power supply;
- actuator control;
- avionics interfaces;
- cockpit control interfaces;
- emergency systems;
- environmental control and pressurization;
- fuel system;
- landing gear control;
- braking system;
- door control;
- cargo locking monitoring;
- sensor network for loading operations.
Cargo System Interfaces
The cargo handling system interacts with multiple aircraft systems.
| Interface | Function |
|---|---|
| Electrical power | Power supply to actuators, sensors and control units |
| Hydraulic system | Possible actuation source for arms, doors or locks |
| Cockpit controls | Pilot command and monitoring of loading operations |
| Structural hard points | Load transfer from lifting system into primary structure |
| Avionics | Alerts, status monitoring and safety interlocks |
| Landing gear | Ground stability and aircraft positioning during loading |
| Door system | Interlocks between door position and lifting operation |
Cockpit Control Logic
The cockpit shall provide clear handling system status.
Possible cockpit indications include:
- door open;
- door closed;
- door locked;
- arms deployed;
- arms retracted;
- twist-lock engaged;
- container secured;
- load imbalance;
- emergency stop active;
- winch mode active;
- ground clearance warning;
- loading operation inhibited.
Systems Deliverables
TRL3 systems deliverables include:
- preliminary systems block diagrams;
- power budget;
- actuator architecture options;
- sensor architecture;
- cockpit interface concept;
- interlock logic;
- emergency control logic;
- systems risk matrix.
WP8 — Risk Assessment and Safety Analysis
Purpose
The TRL3 risk assessment identifies the technical risks that may prevent the architecture from maturing toward TRL4.
Major Technical Risks
| Risk | Description | Severity | TRL3 Mitigation |
|---|---|---|---|
| Ventral opening structural penalty | Reinforcements may become too heavy | High | FEA, local optimization, alternative frame concepts |
| Pressurization around cargo door | Door sealing and pressure loads may be complex | High | sealing study, load cases, pressure frame design |
| Cargo lifting load concentration | ISO corner loads may create high local stresses | High | load path modelling, reinforcement design |
| Robotic arm mass penalty | Handling system may reduce payload or range | High | mass tracking, architecture simplification |
| CG shift during loading | Aircraft may become unstable during container transfer | High | ground stability model, operational limits |
| Landing gear integration | Nacelle-mounted gear may require major reinforcement | Medium to High | nacelle load analysis, Q400 reference comparison |
| Aerodynamic drag | Large fuselage and nacelles may reduce range | Medium | CFD, drag breakdown, configuration refinement |
| Systems complexity | Autonomous loading may add certification difficulty | Medium to High | FMEA, redundancy logic, phased automation |
| Aeroelastic behaviour | High wing and large fuselage may introduce coupling effects | Medium | preliminary aeroelastic screening |
Risk Mitigation Logic
TRL3 risk mitigation is based on:
- conservative sizing;
- early simulation;
- critical load path analysis;
- redundancy concepts;
- physical demonstrator planning;
- industrial review;
- failure mode analysis;
- configuration iteration.
Safety Philosophy
The ISO-Plane cargo handling system must be treated as an aircraft safety-related system, not as ordinary ground support equipment.
This means that TRL3 shall consider:
- fail-safe behaviour;
- controlled failure modes;
- emergency stop logic;
- mechanical locking;
- clear crew indications;
- maintenance inspections;
- safe ground exclusion zones;
- prevention of inadvertent release;
- prevention of flight with unsecured cargo.
WP9 — Industrial Interface
Purpose
TRL3 initiates structured technical dialogue with industrial stakeholders.
The objective is not yet procurement, but technical validation of assumptions.
Potential Stakeholders
Potential technical discussions may involve:
- engine manufacturers;
- landing gear suppliers;
- aerospace structural engineering partners;
- cargo handling system suppliers;
- actuator suppliers;
- embedded systems suppliers;
- certification advisors;
- airframe manufacturers;
- composite and metallic structure specialists;
- simulation and testing laboratories.
Industrial Questions
The TRL3 industrial interface shall prepare answers to the following questions:
- Is the selected engine class realistic for the mission?
- Can Q400-derived landing gear components be adapted?
- What certification issues are raised by autonomous cargo loading?
- Can the ventral door be manufactured and maintained?
- What structural technologies are best suited to the fuselage?
- What level of redundancy is expected for cargo lifting?
- What test articles would be most valuable at TRL4?
- What subsystem could be developed by an industrial partner?
- Which parts of the project remain open-source and which may support private industrial bricks?
Industrial Deliverables
The industrial interface package shall include:
- short technical brief;
- configuration summary;
- mass and performance assumptions;
- critical risk list;
- subsystem questions;
- preliminary supplier mapping;
- list of data required from partners;
- TRL4 demonstrator proposal.
Environmental and Sustainability Considerations
TRL3 also introduces a more rigorous environmental review.
The ISO-Plane is a fuel-powered turboprop aircraft concept, therefore its environmental performance must be assessed early.
TRL3 Environmental Studies
The environmental work shall include:
- updated fuel burn model;
- mission-based CO₂ emission estimate;
- comparison with alternative freight modes for relevant missions;
- sensitivity to payload factor;
- sensitivity to mission distance;
- structural mass reduction strategies;
- Sustainable Aviation Fuel compatibility study;
- preliminary lifecycle analysis preparation;
- maintainability and repairability considerations;
- potential reuse of existing certified components.
Sustainability Levers
Possible sustainability levers include:
- use of efficient turboprop propulsion for regional and medium-range cargo missions;
- structural weight reduction;
- mission optimization;
- high payload utilization;
- SAF compatibility;
- modular containerized operations;
- reduced need for heavy ground handling infrastructure;
- long service life design;
- maintainable and inspectable cargo mechanisms.
Environmental Risk
The main environmental risk is that the aircraft may only be competitive on specific mission profiles.
TRL3 shall therefore avoid generic claims and focus on mission-specific environmental relevance.
Potential favourable missions include:
- remote logistics;
- humanitarian relief;
- disaster response;
- urgent industrial logistics;
- firefighting with containerized water systems;
- military or civil protection support;
- cargo delivery to regions with limited ground infrastructure.
TRL3 Verification Methods
TRL3 verification relies on a combination of analytical and preliminary experimental methods.
| Method | Application | Expected Confidence Level |
|---|---|---|
| Hand calculations | first-order sizing and sanity checks | preliminary |
| Finite Element Analysis | structural stresses and load paths | medium |
| CFD | aerodynamic refinement | medium |
| Multibody simulation | cargo handling kinematics | medium |
| Mass modelling | aircraft mass and CG consolidation | medium |
| Failure analysis | safety and redundancy logic | preliminary to medium |
| Subscale testing | early validation of mechanisms or structural details | medium if available |
| Industrial review | external validation of assumptions | qualitative but important |
Digital Mock-Up Requirements
The TRL3 digital mock-up must evolve from a visual 3D model into an engineering model.
The digital mock-up shall include:
- consistent aircraft coordinate system;
- defined reference planes;
- fuselage frames;
- wing box geometry;
- cargo bay volume;
- container envelope;
- door kinematics;
- landing gear envelopes;
- engine nacelle envelopes;
- lifting system geometry;
- maintenance access zones;
- human access zones;
- structural hard points;
- mass property allocation.
The mock-up shall be suitable for:
- geometry checks;
- interference detection;
- mass allocation;
- CFD simplification;
- FEA preparation;
- communication with industrial partners;
- TRL4 demonstrator definition.
TRL3 Deliverables
By the end of TRL3, the ISO-Plane program shall deliver a coherent technical package demonstrating that the aircraft architecture can survive detailed engineering scrutiny.
Structural Validation Package
The structural package shall include:
- global structural calculation report;
- local structural calculation report;
- fuselage finite element model;
- central wing box finite element model;
- ventral opening reinforcement study;
- cargo handling load path study;
- landing gear load introduction study;
- fatigue-sensitive zone identification;
- structural mass estimate;
- list of assumptions requiring physical testing.
Aerodynamic Refinement Package
The aerodynamic package shall include:
- CFD simulation report;
- updated drag breakdown;
- refined lift and drag polar;
- propeller slipstream interaction assessment;
- updated takeoff and landing performance;
- cruise performance estimate;
- updated range estimate;
- payload-range curve;
- aerodynamic risk assessment.
Cargo Handling Package
The cargo handling package shall include:
- mechanism architecture description;
- kinematic model;
- arm deployment and retraction study;
- ISO corner interface study;
- twist-lock integration logic;
- emergency winch concept;
- load transfer analysis;
- preliminary actuator sizing;
- safety interlock logic;
- preliminary FMEA.
Ventral Door Package
The ventral door package shall include:
- three-panel door mechanism description;
- kinematic sequence;
- hinge and actuator load estimates;
- locking concept;
- sealing concept;
- pressurization load analysis;
- reinforcement strategy;
- failure scenarios;
- TRL4 test recommendations.
Landing Gear Integration Package
The landing gear package shall include:
- Q400-derived gear integration concept;
- nacelle structural concept;
- retraction envelope;
- ground stability assessment;
- landing load path analysis;
- braking energy estimate;
- compatibility with loading scenarios.
Mass and Balance Package
The mass and balance package shall include:
- updated mass breakdown;
- empty mass estimate;
- payload and fuel allocation;
- CG envelope;
- loading and unloading CG analysis;
- sensitivity to cargo position;
- MTOW feasibility assessment.
Systems Architecture Package
The systems package shall include:
- electrical architecture;
- hydraulic architecture;
- cargo system control architecture;
- cockpit interface concept;
- sensor and actuator interface matrix;
- emergency power and backup logic;
- preliminary systems safety analysis.
Risk and Roadmap Package
The roadmap package shall include:
- updated risk register;
- technical gap list;
- mitigation plan;
- TRL4 demonstrator priorities;
- industrial engagement plan;
- preliminary certification discussion points;
- updated project schedule.
TRL3 Acceptance Criteria
TRL3 may be considered successful if the following criteria are met:
| Domain | Acceptance Criterion |
|---|---|
| Structure | Critical load paths are identified and preliminary sizing shows feasible margins |
| Ventral door | Door architecture is compatible with pressurization, loading and structural continuity |
| Cargo handling | Container lifting system has credible kinematics and validated preliminary load paths |
| Aerodynamics | Updated aerodynamic model supports the mission envelope within acceptable uncertainty |
| Landing gear | Nacelle-mounted gear integration remains compatible with cargo bay geometry |
| Mass and balance | Aircraft remains within a credible 30-tonne-class MTOW target |
| Systems | Main system interfaces are identified and no blocking incompatibility is found |
| Safety | Major failure modes are identified with preliminary mitigation logic |
| Industrial readiness | A technical package exists for credible external review |
Path Toward TRL4
TRL4 will focus on validation in a laboratory or relevant subsystem environment.
The transition from TRL3 to TRL4 requires moving from analytical confidence to demonstrator-based confidence.
TRL4 Priorities
The recommended TRL4 priorities are:
- subscale ventral door demonstrator;
- structural test article for fuselage opening reinforcement;
- cargo handling mechanism demonstrator;
- twist-lock and arm load test bench;
- ground loading scenario demonstrator;
- landing gear packaging validation mock-up;
- CFD-to-wind-tunnel correlation if feasible;
- cockpit control interface prototype;
- preliminary certification discussions;
- industrial feasibility assessment.
Candidate Demonstrators
| Demonstrator | Purpose | Priority |
|---|---|---|
| Ventral door structural demonstrator | Validate hinges, locks, frame loads and sealing logic | Very high |
| Cargo lifting test bench | Validate arm loads, twist-lock interfaces and emergency lowering | Very high |
| Fuselage frame section | Validate reinforcement around large lower opening | High |
| Ground loading mock-up | Validate loading from ground and truck trailer | High |
| Systems control bench | Validate interlocks, sensors and cockpit logic | Medium |
| Aerodynamic model | Validate CFD assumptions through wind tunnel testing | Medium |
Certification Preparation
TRL3 is not a certification phase, but it must already identify future certification issues.
The following certification topics shall be monitored:
- pressurized cargo compartment with large ventral opening;
- structural substantiation of door and locking systems;
- emergency release and retention of cargo;
- autonomous ground loading operations;
- cockpit-controlled cargo handling system;
- human safety during ground operations;
- aircraft stability during loading;
- failure of powered lifting systems;
- flight prevention with unsecured container;
- system redundancy and monitoring;
- maintenance inspection intervals;
- fatigue and damage tolerance around cargo opening;
- compliance strategy for cargo restraint.
A certification advisor should review the TRL3 architecture before TRL4 demonstrator commitments.
Strategic Vision
TRL3 transforms ISO-Plane from a promising aircraft architecture into a structured engineering program.
It is the stage where:
- feasibility becomes measurable;
- risks become visible;
- design choices become traceable;
- technical credibility begins;
- industrial dialogue becomes possible;
- future demonstrators can be defined.
The purpose of TRL3 is not to prove that every part of the ISO-Plane is final.
Its purpose is to prove that the architecture is strong enough to deserve the next level of investment, testing and industrial involvement.
Summary
ISO-Plane TRL3 is the analytical and experimental proof-of-concept phase of the program.
It validates the most critical assumptions behind the aircraft:
- the 20-foot ISO container can be integrated into the fuselage;
- the ventral loading architecture can be structurally investigated;
- the autonomous loading system can be analysed through realistic load paths;
- the Q400-derived landing gear concept can be assessed in nacelle integration;
- the high-wing turboprop configuration can be refined aerodynamically;
- the mass and balance model can be consolidated;
- the program can prepare for subsystem demonstrators.
By the end of TRL3, the ISO-Plane shall no longer be only a concept.
It shall become a technically supported aircraft definition ready for demonstrator-oriented development.
ISO-Plane — Engineering the next generation of container air logistics.